Casting a Master Pattern with BK-PMH73 PU Resin

When casting a rigid prototype or master pattern in a silicone mold, the work starts before the two resin components meet. BK-PMH73 has an approximate working time of 90 seconds at 23°C (73°F). That short window needs to accommodate mixing, pouring and the specified vacuum procedure—not just stirring the resin.

This guide explains the process described in the supplied BK-PMH73 TDS. It is a preparation guide, not a record of a completed customer project. Begin with a trial using your actual equipment and mold.

Understand the roles of the resin and the mold

BK-PMH73 is the two-component rigid polyurethane resin poured into the cavity. The silicone mold holds the shape during casting and curing. The resulting rigid casting can be used as a prototype or a master pattern for mold-making work.

The resin and silicone are different materials. Use BK-PMH73's own mixing ratio and processing guidance for the casting resin; silicone mixing or curing times do not apply to it.

Prepare before starting the clock

Place the clean, dry mold and vacuum equipment within reach. Prepare two clean, dry mixing cups and pre-weigh Part A and Part B at a 1:1 weight ratio. For example, equal masses of A and B satisfy that ratio; the TDS does not establish an equivalent volume ratio.

Moisture control is part of preparation. The TDS notes that moisture can react with isocyanate-containing PU systems, causing bubbles and processing defects. Keep the components sealed until needed and avoid introducing water through the mold, cups or handling process.

Mix thoroughly, then pour promptly

The specified procedure is to pour Part A into Part B, transfer the combined resin back and forth between the two cups twice, and mix thoroughly while scraping the walls and bottoms. Pour the mixture into the silicone mold immediately afterward.

Keep the approximate 90-second working window at 23°C (73°F) in mind when planning this sequence. A longer mixing or transfer routine leaves less time for pouring and vacuum treatment. The exact result depends on the actual material temperature and other process conditions.

Include vacuum time in the trial

The TDS places vacuum treatment after pouring: put the filled mold in the chamber, reach the equipment's target/full-vacuum reading, hold for approximately 30 seconds, and vent slowly back to atmospheric pressure.

Watch for foaming or overflow. Before relying on this method for production, confirm that the entire process can be completed before gelation. The document gives no numerical vacuum-pressure setting; the equipment reading and holding time must be considered together in a process trial.

Separate demolding from full-property development

At approximately 23°C (73°F), the TDS gives around 20 minutes before demolding, provided the casting is sufficiently set, and approximately one hour before initial use. These are different milestones. Full physical properties may take longer to develop.

Record the resin mass, mold geometry, room conditions, actual material temperature and mixing procedure during the trial. The TDS identifies these as factors affecting the approximate processing times. A successful trial with one casting does not establish the same timing for every size or mold.

Account for warmer conditions

Where ambient temperature exceeds 23°C (73°F), the document describes refrigerating A and B separately in tightly closed containers for at least three hours. Its workshop observations at 5–8°C (41°F–46°F) gave approximately 120 seconds of working time. This observation does not establish a universal cooling temperature or a guaranteed two-minute window.

Keep moisture and condensation out of the components, leave containers sealed until ready, and wipe them dry before opening. Read the product-specific SDS before deciding on handling and cooling arrangements.

What to check before moving beyond a trial

Check whether mixing, pouring and vacuum treatment fit within the working window, whether the casting is sufficiently set before removal, and whether it meets the requirements of the intended prototype or master pattern. Mechanical and thermal design limits need their own validation: the TDS marks several performance values as transcribed and not independently verified.

Use ventilation, chemical-resistant gloves and eye protection as specified in the TDS, and consult the product-specific SDS. Do not transfer safety information or performance ratings from a different resin or from the silicone used for the mold.

Plan your next casting trial

See the BK-PMH73 material overview for the processing table. If you need help discussing the mold or trial, contact BK Silicone with the intended part, size and quantity.

Sam Zhong
Sam Zhong
Founder of BKSilicone · Silicone Engineer

Follow Me

Sam Zhong is the founder of BKSilicone and has over 15 years of hands-on experience in silicone materials and mold-making applications. He works closely on custom mold projects, material testing, and real production use cases.